Thunderbird Operations – Camp
Client: Thunderbird Operations – Camp
Project Value: $1.5 million
Project Dates: March 2022 – September 2022
Project Description: MMJ Electrical Pty Ltd successfully delivered the complete electrical scope for the 240-person Thunderbird Village, constructed for McNally Mining and Resources.
Delivered over a 6-month program, the works included all pit and pipe, cabling supply and installation, switchboard installations, and modular building terminations, complexing and commissioning. Delivering an integrated electrical network from power generation through to final outlets across the entire village.